Customer wanted the ability to export the project answers, currently in progress and not completed, review them outside of the project, updated the answers needed, and reimport it into the project so that answers from the projects are all reviewed and updated in bulk.
This is almost similar to the export content and reimport using the "Import Updates". But for this customer, they are looking to do the same for the projects.
Use case: The team would like to export the answers/changes to Excel, work on them offline, and then re-import the updated version back into the project. Currently this is not possible; changes and tracking must be done within the specific project, with the Activities tab being the only method to review edits.
Impact: For very large questionnaires, the inability to export, edit, and re-import forces all work to be done in-app question by question, which is time-consuming and cumbersome for large-volume projects.
Customer: Juniper AM, Jacquie Berry
Ticket: TKT-217666